5 | P a g e
G-4 Implementation schedule
In order to construct a model approximately five weeks would be needed. The first week
would be to finish designing any changes to the product and ordering parts to begin construction.
Once parts are acquired construction would begin in week two starting with the locking
mechanism. The third week would consist of construction of the control circuit and testing using
logical inputs provided from a DIP switch. The fourth week would be construction of the
accelerometer circuit and the power system. The fifth and final week all systems, whether
bought or constructed, are wired together and combined into the bottle for the finished product.
All weeks are considered to be five days of the week with eight hour work days. Staff will be a
group of four working part-time (less than 32 hours).
Week 1:
1-2 days for fixing possible safety issues and design flaws
1-2 days for drawing printed circuit boards and submit orders for all parts
1-2 days for acquiring local parts and fabrication of housing
Week 2:
1 day for fixing locking cylinder into circuit housing and fix mounting clamps onto lock housing
2-3 days for fabricating locking mechanism and fixing DLA into locking mechanism
1-2 days for quality and safety testing
Week 3:
2-3 days for construction of control circuit
2-3 days for testing of control circuit and troubleshooting.
Week 4:
2-3 days for construction of accelerometer circuit
1 day for construction of power system
1-2 days of system testing before final construction
Week 5: